One. Before opening the suspension chain conveyor line, you should check the tightness of the lower conveyor belt. The buckle should be buckled. The transmission components such as gears, chain plates and bearings should be viewed to see if it is outstanding. The rollers and protective equipment should look down. Neat, electrical maintenance zero or grounding is outstanding, the width of the drum should be together with the conveyor belt.

two. When the suspension chain conveyor line is started, it should not be placed in any material inside, and it should be transported at no load. After there is no problem in comparison and transportation, then the materials are loaded. Pay special attention not to install the material and then start the assembly line.

three. Before the mobile suspension chain conveyor line is launched, it should be checked whether the wheel is symmetrically wedged, and there is no wedge; the fixed suspension chain conveyor line should be equipped under the premise of stability. When multiple machines work in parallel, the center of each machine should be more than 1 m above the aisle. Look for obstacles around the hanging chain conveyor line that affect the job.

four. When transporting large quantities of cargo, the ends of the suspension chain conveyor should be equipped with protective equipment, such as a loading plate or gate.

Hanging chain conveyor line safety precautions

Fives. The discharge height of the suspension chain conveyor must be adjusted in the case of parking. After adjusting the height, you must insert the secure pin and tighten the adapter nut.

six. The time of feeding on the suspension chain conveyor line should be based on the center of the conveyor belt and adjust the height to prevent the belt and the roller from being severely impacted during the process of discharging the material. The material should increase evenly.

Seven. If several suspension chain conveyors are feeding in series, they should be started on the side of the discharge, and the loading can be carried out after all the conveyors are working properly.

Eight. In case of sudden situation, for example, when the power is cut off, the power supply should be blocked immediately and the cargo on the hanging chain conveyor line should be cleaned up. After the electricity is coming, the fault should be checked and the power supply should be connected.

nine. The suspension chain conveyor line should be prevented from passing over or under the suspension chain conveyor line during the operation. When the conveyor belt is in a slippery condition, the power supply should be blocked and the hand should be pulled. Stop the inspection and maintenance during the work.

ten. When the operation demand of the suspension chain conveyor line is stopped, the material should be stopped first, and the material on the conveyor belt should be processed before the machine can be shut down. If several conveyors are required to stop in tandem operations, they should be shut down from the side of the discharge.

eleven. In the operation of the suspension chain conveyor line, the operation of the conveyor should be investigated at any time. If the transportation is found to be biased or loose, it should be shut down for inspection.

twelve. After the operation of the suspension chain conveyor line is completed, the power supply should be blocked first, the power switch box should be locked, and then the materials on the conveyor line should be finished. Finally, the motor should be covered with a shield.